Worked estimate · Fence replacement

Build the cost.
Then build the estimate.

A linear-foot price can hide a lot of assumptions. Walk through a small fence job from measured scope to labor hours, direct cost and selling price, then see what happens when the work takes longer.

Learning example, not a bid or price guide. Every quantity, rate and duration below is hypothetical. They are not Mississippi prices, industry averages, a material takeoff or an installation specification. Use verified site measurements, supplier quotes and your own crew history.

1. Define exactly what the price covers

Example scope: remove and replace 96 linear feet of 6-foot wood privacy fence on an agreed alignment. No gates are included. Assume ordinary access, one mobilization and no unusual demolition or excavation conditions. Final materials, layout and installation requirements must be confirmed before a real quote.

Included in this example

  • Removal and disposal of the existing 96-foot run.
  • New posts, concrete, rails, pickets and fasteners, represented here by one hypothetical supplier material total.
  • Layout, installation and ordinary cleanup labor.
  • Delivery, equipment rental and disposal costs.

Not silently included

  • Gates, staining, retaining work or landscaping restoration.
  • Surveying, permit charges or utility relocation.
  • Rock, buried concrete or other concealed obstacles.
  • Customer sales tax, if applicable.

These are scope boundaries, not a recommendation to exclude necessary work. Confirm requirements and who will handle each item before issuing a real estimate.

2. Estimate labor in person-hours

Two people working for four hours means eight person-hours, not four. Count the work once and use a labor cost rate, not your customer billing rate.

Swipe the table sideways to see all columns.

TaskPerson-hoursExample labor cost
Layout, loading and setup4$140
Remove old fence and load debris8$280
Post work and fence installation20$700
Cleanup, disposal run and closeout4$140
Total36$1,260

36 hours × $35 per person-hour = $1,260. In this example, $35 is a hypothetical fully loaded direct labor cost including the employer costs allocated to that labor. It is not an employee wage recommendation. Do not add the same burden again elsewhere.

Person-hours do not establish elapsed schedule. Post-setting requirements, cure time, weather and return trips can change the schedule. Add the associated labor, equipment and mobilization costs when they apply.

3. Build the direct job cost

Swipe the table sideways to see all columns.

Cost categoryWhat's insideExample cost
MaterialsPosts, concrete, rails, pickets, fasteners; hypothetical total including purchase tax and waste allowance$1,450
Labor36 person-hours × $35$1,260
DisposalDisposal fees only; handling labor above$175
EquipmentRental cost only; operator labor above$125
DeliverySupplier delivery, not already in material total$75
Total direct job cost$3,085

Double-count check: This is a cost build-up, not an installed-price-per-foot estimate. Do not add a second installed fence line, separate post labor or another removal labor charge on top of these same costs.

No separate contingency or office overhead line is included in this illustration. Decide how your business recovers those costs. Label any allowance clearly and use one consistent method rather than hiding it in several places.

4. Set the selling price deliberately

At an illustrative 35% markup$4,164.75Before customer sales tax, if applicable

Direct cost: $3,085.00
Markup amount: $1,079.75
Gross margin on this cost basis: 25.9%

$3,085 × 1.35 = $4,164.75

$1,079.75 ÷ $4,164.75 = 25.9%

A 35% markup is not a 35% margin. The $1,079.75 spread is not take-home pay: it still has to cover any overhead and other costs not allocated above. The example does not prescribe a target markup.

Check your numbers with the existing EZ-Est markup and margin calculator. Do not multiply a pre-marked-up selling rate by another markup unless that is intentional.

5. Stress-test the labor assumption

The example selling price stays fixed. Change the extra person-hours and loaded labor cost to see the effect on the remaining cost-to-price spread.

Added labor cost$280.00Total direct cost: $3,365.00
Remaining spread: $799.75
Margin on this cost basis: 19.2%

Assumes only labor changes. Materials, equipment, disposal and additional visits may also change. These inputs are not sent anywhere or persisted.

6. Turn the math into customer-facing scope

Internal cost detail and customer-facing quote structure are different things. A single clearly scoped fixed-price line can be easier to read than exposing your internal cost model.

SAMPLE ONLY — NOT A CUSTOMER QUOTE

Remove and replace 96 linear feet of 6-foot wood privacy fence along the agreed alignment. Includes new posts, concrete, rails, pickets and fasteners; removal and disposal of the existing fence; delivery; installation; and ordinary cleanup.

Example fixed price: $4,164.75 before customer sales tax, if applicable.

No gates or staining included. Surveying, permit charges, utility relocation, unusual excavation and landscaping restoration are not included in this example and must be resolved before quoting the actual job.

Before approval: confirm final materials and layout, property-line responsibility, utility-location process, required permits, access, schedule, payment terms, quote validity and how concealed conditions or customer changes will be documented and priced.

Use this structure with your verified numbers in the fence estimate template, then build the estimate in EZ-Est. Review the output before sending. This sample is not a complete contract.

Before you send: the five-minute review

Learn from the job you finish

Record estimated and actual person-hours by task, supplier totals, disposal receipts and the reason for any difference. Separate a missing scope item from slower production. On the next similar job, change the assumption that was wrong instead of increasing every number blindly.

Why not give one universal fence price per foot?

Length alone does not describe a fence job. Height, material selection, gates, demolition, access and ground conditions change scope and cost. A unit selling price can still be useful when its inclusions are explicit. It is not a substitute for checking the job.